    The Parramatta Traffic Committee at its meeting held on 20 November 2025 considered a report on this matter. Council at its meeting on 9 December 2024 considered the Committee’s recommendation and resolved:

    1. That Council approve the installation of a roundabout at the intersection of Fitzwilliam Road and Tucks Road, Toongabbie as shown in the attached plan. (Please see the Council report for detail)

    2. That the existing refuge island in Fitzwilliam Road, Toongabbie east of Willmott Avenue be upgraded to comply with current standards as shown in the attached plan.

    3. That a new pedestrian refuge island be installed in Ballandella Road, Toongabbie at Fitzwilliam Road as shown in the attached plan.

    4. That a median island be installed in Fitzwilliam Road between Tucks Road to the east of Willmott Avenue restricting access in Willmott Avenue to left in left out as shown in the attached plan.

    5. That a shared path be installed along the northern side of Fitzwilliam Road through the intersection with Tucks Road as shown in the attached plan.

    6. That Council staff in consultation with CDC Hillsbus investigate the exit of the western side service road to improve sight lines for buses when entering Fitzwilliam Road and that any changes to the plans be shared with CDC Hillsbus and Transport for NSW for concurrence prior to commencing construction.

    7. That Council staff investigate the provision of a shared path on the south side of Fitzwilliam Road between the pedestrian refuge island west of Tucks Road and Ballandella Road, Toongabbie.

    8. That recommendations 1 to 7 be subject to funding being available for the construction of the traffic facilities.

    To read the report and minutes of the meeting CLICK HERE

    • Council report - page No. 36
    • Minutes of the PTC meeting - page Nos. 39 - 53
    • PTC report - page Nos. 152-184

    Council anticipates construction will be completed this calendar year. Please follow the project on Participate Parramatta for further updates.