Doyle Ground Sports Facility Improvements

Project background

City of Parramatta Council is delivering major upgrade works at Doyle Ground, a key sporting facility located near Parramatta CBD. The upgrades aim to transform the site into a high-quality district sporting facility.

The proposed works were developed in line with the Heart of Play Master Plan adopted by Council in July 2021.

The project will be delivered in two stages, as outlined below. Stage 1 upgrades are currently underway with construction and environmental impacts being actively managed to minimise disruption. Any activities involving potential hazards, such as asbestos removal, will be undertaken in accordance with strict safety requirements to protect public health and safety.

The proposed Stage 2 works including the draft concept plan were placed on public exhibition, and the community was invited to review until 5pm on Monday 3 August 2026.

September 2026

Further investigations at Doyle Ground have shown that fibro fragments are found in soil in an area larger than previous testing indicated. City of Parramatta, in consultation with experienced specialists, has developed a Remediation Action Plan to effectively manage the asbestos. Rigorous environmental and public health controls will be used throughout the planned seven (7) week remediation program.

Playground and fitness equipment area closed for excavation works on Tuesday 23 and Wednesday 24 June 2026

Over the past few weeks, Council has overseen construction works at Doyle Ground to deliver improved drainage and upgrades to sporting facilities.  Despite soil studies being conducted prior to the start of works, excavation in the work area revealed unexpected fibro fragments buried within the soil underneath the grassed surface of the park.  Excavation of the area, and the removal of contaminated soil, will take place on Tuesday 23 and Wednesday 24 June 2026. 

Construction for Stage 1 works to start from Tuesday 19 May 2026

Community feedback showed strong support for the proposed works, with 70% fully supporting the proposal and a further 28% supporting it to some extent. Construction of Stage 1 Doyle Ground Sports Facility Improvements is scheduled to commence on Tuesday 19 May 2026 and expected to be completed in early-2027, with the sports field re-opened in mid-2027 following turf establishment. The circuit path, toilets, playground, and fitness equipment areas will remain open until further notice. 