The plan to upgrade the social, sporting and recreation facilities at Binalong Park, Toongabbie is progressing.
 
Council has secured funding from the Federal Government’s Major and Local Community Infrastructure Program and will begin early site investigation work which will inform the scope for Stage 1.
 
The investigations include: a tree survey, spatial measurements, testing for contaminants, and engineering analyses.
 
Consultation with Toongabbie Public School, sporting groups and the community will be held as the detailed concept designs are being developed.
 

A new sports and communities amenities building is proposed to provide direct and accessible connection with all of the recreational and sports activities provided within the park.

Sports related amenities such as change rooms, kiosks and referees rooms are positioned to its eastern façade. The master plan also specifies community related facilities including public toilet and a multifunction community space and additional public recreation facilities and outdoor meeting areas.

It is proposed the tennis amenities building is upgraded to ensure that it is complies with the Disability Discrimination Act and includes a kitchenette, public toilet and picnic areas.

We understand the sports fields at Binalong Park are important assets for the sports clubs and community. 

Planned improvements in the first stage of works include upgrading or installing new LED sports field lighting to meet current Australian lighting standards.

Binalong Park is well known for its significant eucalypt trees. Council wants to ensure that they remain an integral part of the Park’s character. 

To protect the trees, a detailed arborist assessment will evaluate their health and identify protection measures for construction.

Carpark improvements included in the upgrade works are:

•    Separate entry and exit points
•    Relocation of the carpark further along Binalong Park, away from the Fitzwilliam intersection, to reduce congestion
•    A circuit path connecting the carpark with the sports fields and recreational amenities
•    A more efficient carpark layout
To deliver these improvements, the number of parking spaces will decrease from 104, including 2 accessible spaces, to 92, including 2 accessible spaces.

This reduction was tested during public exhibition, with no significant objections received. The carpark size and layout will be further refined through the design, consultation and approval process.

The Binalong Park Master Plan sets out a 20 year vision to align future work at the park by:

  • Identifying opportunities to improve the park layout and increase provision of recreational activities
  • Identifying opportunities to provide new amenities buildings and multi-purpose indoor community spaces.
  • Improving site safety, sight lines and pedestrian connectivity.

 

Council conducted 3 phases of community consultation to inform the draft master plan:

  • Phase 1 consultation was conducted 7 December 2020 to 4 February 2021. A total of 413 responses were received. See resources section for full report.
  • Phase 2 consultation was conducted from 19 April to 10 May 2021 with a total of 352 responses were received. See resources section for full report
  • Phase 3 consultation (public exhibition of the draft masterplan) was conducted from 31 May to 25 June 2021 with a total of 42 submissions were received. See resources section for the full report.

 

A total of 807 responses was collected across 3 rounds of consultation. Overall, Council’s suggestions to improve Binalong Park was well received. The community were enthusiastic to see improvements to this much loved park. The general sentiment towards the master plan process was very supportive with participants welcoming the proposed improvements to the park.

Many participants echoed the suggested park improvements and provided insight to local concerns and issues. Timed parking was unpopular and will not be included as part of the draft master plan. Any plans for timed parking will require further community consultation.